Análisis comparativo de costo y tiempo en pavimentos con losas optimizadas tradicionales y flexibles Simbal 2023.

dc.contributor.advisorBurgos Sarmiento Tito Alfredo
dc.contributor.authorCelis Odar, Paola Elizabeth
dc.contributor.authorSoto Castro, Joule Phili
dc.date.accessioned2024-10-25T17:59:06Z
dc.date.available2024-10-25T17:59:06Z
dc.date.issued2024-10
dc.description.abstractEl presente trabajo de investigación se realizó en el distrito de Simbal, provincia de Trujillo, departamento de La Libertad, donde se realizó el análisis comparativo de costo y tiempo con los diseños de pavimento de losas optimizadas, tradicionales y flexible, para lo cual se empleó un diseño no experimental, transversal y descriptivo; donde se evaluó tres poblaciones representados por los tipos de diseño mencionados asimismo se realizaron los estudios de tránsito, mecánica de suelos y topografía para la obtención de datos, para el análisis de datos se usó la técnica estadística descriptiva, el problema radica en que a lo largo de los años se ha venido pavimentando tradicionalmente con un pavimento flexible; que frente al pasar de los años así como al tráfico de vehículos circulantes la vida útil de los mismos ha bajado, representándose en fallas de la carpeta de rodadura, ocasionando que se eleve el costo de la vida útil del pavimento, por otra parte en Trujillo y en el Perú no es muy usado la pavimentación con concreto y mucho menos las nuevas metodologías que se desarrollan en base a esto como es la técnica de lozas optimizadas en las que se tiene pocos profesionales especializados en este campo, se obtuvo que para un periodo de diseño de 20 años la estructura diseñada con losas optimizadas de concreto presenta ventajas significativas de costos frente a los pavimentos de concreto rígido y asfalto tradicional llegando a un valor estimado mediante un análisis de costo de ciclo de vida de S/ 1,937,892.54, S/ 2,038,850.15 y S/ 2,404,112.99; en relación al tiempo esperado mediante el método de la ruta crítica la relación está entre 90, 80 y 49 días calendarios y empleando la técnica de evaluación y revisión de programas se estimó un tiempo de 102, 95 y 51 días calendarios respectivamente. Del análisis comparativo se concluyó que el diseño con losas optimizadas presenta menores costos para un periodo de análisis de 20 años y un tiempo de construcción no significativo en comparación con las otras metodologías.
dc.description.abstractThe present research work was carried out in the district of Simbal, province of Trujillo, department of La Libertad, where the comparative analysis of cost and time was carried out with the optimized, traditional and flexible slab pavement designs, for which a non-experimental study, cross-sectional and descriptive design; where three populations represented by the types of design mentioned were evaluated, traffic studies, soil mechanics and topography were also carried out to obtain data, for the analysis of the data the descriptive statistical technique was used, the problem is that throughout Over the years it has traditionally been used paved with flexible pavement; that over the years, as well as the traffic of circulating vehicles, its useful life has decreased, generating failures in the rolling surface, causing the cost of the useful life of the pavement to increase, on the other hand in Trujillo and Peru concrete pavement is not widely used, much less the new methodologies that are developed based on it, such as the optimized tile technique in which there are few professionals specialized in this field, it was obtained that for a design period of 20 years . , the structure designed with optimized concrete slabs presents important cost advantages over traditional rigid concrete and asphalt pavements, reaching an estimated value through a life cycle cost analysis of S/ 1,937,892.54, S/ 2,038,850.15 and S/ 2,404,112.99 ; In relation to the expected time using the critical path method, the relationship is between 90, 80 and 49 calendar days and using the program evaluation and review technique, a time of 102, 95 and 51 calendar days was estimated respectively. From the comparative analysis, it was concluded that the design with optimized slabs presents lower costs for an analysis period of 20 years and a non-significant construction time compared to the other methodologies.
dc.formatapplication/pdf
dc.identifier.urihttps://hdl.handle.net/20.500.14414/22675
dc.language.isospa
dc.publisherUniversidad Nacional de Trujillo
dc.publisher.countryPE
dc.rightsinfo:eu-repo/semantics/openAccess
dc.rights.urihttps://creativecommons.org/licenses/by-nc-nd/4.0/
dc.subjectTECHNOLOGY::Civil engineering and architecture
dc.subject.ocdehttps://purl.org/pe-repo/ocde/ford#2.01.00
dc.titleAnálisis comparativo de costo y tiempo en pavimentos con losas optimizadas tradicionales y flexibles Simbal 2023.
dc.typeinfo:eu-repo/semantics/bachelorThesis
dc.type.versioninfo:eu-repo/semantics/publishedVersion
renati.advisor.dni42141206
renati.advisor.orcid0000-0003-2143-1566
renati.author.dni71234752
renati.author.dni72765431
renati.discipline732016
renati.jurorClaudet Angulo, Kateryne Mercedes
renati.jurorGavidia Samamé, Jhony Ricardo
renati.jurorBurgos Sarmiento, Tito Alfredo
renati.levelhttp://purl.org/pe-repo/renati/level#tituloProfesional
renati.typehttp://purl.org/pe-repo/renati/type#tesis
thesis.degree.disciplineIngenieria Civil
thesis.degree.grantorUniversidad Nacional de Trujillo. Facultad de Ingenieria
thesis.degree.nameIngeniero Civil
Files
Original bundle
Now showing 1 - 1 of 1
No Thumbnail Available
Name:
Celis Odar y Soto Castro.pdf
Size:
20.05 MB
Format:
Adobe Portable Document Format
License bundle
Now showing 1 - 1 of 1
No Thumbnail Available
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed upon to submission
Description: